Inner Mongolia desulfurization agent production line

Project Location: Inner Mongolia, China

Equipment: MTW215 European Grinding Mill

Input Material: limestone

Capacity: 300,000Tons/year

The company purchased 3 sets of MTW215 European version grinding equipment from ZENITH Industry for processing limestone and finished ore powder for power plant desulphurization in the surrounding power plant. The use effect is very good and become the largest power plant desulfurization powder supplier in the surrounding area.

Day operation: 24 hours Feed: limestone, into the mill's mainframe particle size <= 35mm Finished: fineness 250 mesh -325 mesh

client feedback

"We bought before the powder, but also at the customer site to see the state of the world's equipment, on-site feedback is very good, we purchased three sets of equipment, from technical programs, sales process, after-sales service and other convenient, Very good, ZENITH quality, the world state brand, great!

A processing limestone company